Interstate 10 (Papago Freeway)
Interstate 10 (Papago Freeway)
Interstate 10 (Papago Freeway)

Sarival Avenue to Dysart Road

Project Summary Add one general purpose lane and one auxiliary lane in each direction adjacent to existing outside lanes.
Current Development Phase Design (as of February 2007)
Schedule RTP Phase 1 to 2006-2010
Funding accelerated by Valley Mayors - April 2006
Began Engineering and Environmental Study - July 2006
Complete Engineering and Environmental Study - February 2007
Begin final design - Summer 2007
Complete final design - Spring 2008
Project Advertisement - Summer 2008
Begin construction - Mid 2009
Open to traffic - Summer 2010

Divider

On The Move Our Valley Freeway System is part of the 2004 voter-approved Regional Transportation Plan. We are working hard with our transit partners to implement the voters’ vision and are committed to quality, safety, open communication with our neighbors, and minimal inconvenience to the traveling public.