Newman Park TI to Airport TI R/W Fence |
| |
Project No.: |
017 CN 328 H665301C 017-A-NFA |
| |
Location: |
Newman Park Interchange on I-17 to the Airport Interchange in Flagstaff. |
| |
Contractor: |
Beco Construction Company |
| |
Programmed Cost: |
$466,518 |
| |
Scope: |
Construct new right of way fence. |
| |
Expected Project Duration: |
Fall 2008 to Spring 2009 |
| |
| Statewide Dynamic Message Sign Boards/ Phase 8 |
| |
Project No.: |
999 SW 000 H699201C 999-A-NFA (Statewide project being administered by the Flagstaff District) |
| |
Location: |
Two signs will be located on SR 89A (N Sedona and Fairgrounds in Flagstaff) and US 89 MP 462.7NB at Cameron. Two signs will be put in the Yuma District, One in the Tucson District and One in the Holbrook District. |
| |
Contractor: |
CS Construction Inc. |
| |
Programmed Cost: |
$1,068,725 |
| |
Scope: |
Install new Dynamic message board signs. |
| |
Expected Project
Duration: |
Winter 2008 to Summer 2009 |
| |
|
|
Landscaping & Scenic Beautification/Village of Oak Creek |
| |
Project No.: |
010 PM 286 H734501C IM-010-D(200)A |
| |
Location: |
On SR 179 in the Village of Oak Creek |
| |
Contractor: |
Recon Inc. |
| |
Programmed Cost: |
$1,942,490 |
| |
Scope: |
Install landscaping, including irrigation and pedestrian lighting, in area where SR 179 was just reconstructed through the Village of Oak Creek. |
| |
Expected Project
Duration: |
Expected Project Duration Fall 2008 to Spring 2009 |
| |
|
|
Gray Mountain and Gap roadway lighting |
| |
Project No.: |
089 CN 457 HX19701C 089-6-NFA |
| |
Location: |
On US 89 at the Gap MP 497 and at Gray Mountain MP 457. |
| |
Contractor: |
Rural Electric |
| |
Programmed Cost: |
$105,624 |
| |
Scope: |
Install and upgrade street lighting at both locations. |
| |
Expected Project
Duration: |
Winter 2008 to Spring 2009 |
| |
|
|
I-15 Spot Pavement Repair |
| |
Project No.: |
015 MO 013 H756601C 015-A-NFA |
| |
Location: |
On I-15 in the Virgin River Gorge |
| |
Contractor: |
Interstate Rock Products Inc. |
| |
Programmed Cost: |
$1,835,528 |
| |
Scope: |
Repair spot areas of pavement both north and south bound in the Virgin River Gorge on I-15 |
| |
Expected Project Duration: |
Fall 2008 to Winter 2008 |
| |
|
|
| SR 179 Village of Oak Creek to Y (Project 1 and 2) |
| |
Project No.: |
STP-TEA-A(001)B and STP-TEA-A(002)B |
| |
Location: |
Project 1 is from MP 304.5 (1 mile south of Village of Oak Creek) to MP 310.4 (Back o’ Beyond) and
Project 2 is from MP 310.4 to 313.4 (the “Y”) in the City of Sedona. |
| |
Contractor: |
Southwest Asphalt Paving (Project 1) |
| |
Programmed Cost: |
Project 1 $36,114,000
Project 2 $51,750,000 |
| |
Scope: |
Projects consist of complete rebuild of highway to a multimodal, two lane parkway. |
| |
Expected Project Duration: |
Project 1 Completed
Project 2 Spring 2008 to Spring 2010 |
| |